Scheduled Lift Testing – Brayford Campus

Next week, Schindlers will be on-site to test the below lifts to the described schedule. The inspection can take anything from 1 to 1.5 hours of downtime which may be quicker or longer depending on how the test goes.

Wednesday 22nd June

08:30-10:00 Alfred Tennyson Goods lift

10:00-11:30 Alfred Tennyson Powered platform

12:30-14:00 Janet Lane-Claypon lift

14:00-15:30 Bridge House lift

Friday 24th June

08:30-10:00 Sports & Human Performance lift

10:00-11:30 Village Hall lift

12:30-14:00 Enterprise Building lift

14:00-15:30 Student Wellbeing lift

We apologise for any inconvenience caused. If you require any further information, please contact the Estates Support Desk at estatessupport@lincoln.ac.uk