Campus Works

Please check this page regularly to see the latest information in regards to construction, refurbishment and maintenance activities. We make every effort to minimise any disruption, and to give advance notice of anything planned.

Planned Works on Brayford Campus

The Lincoln Medical School project is well underway on the Brayford Campus. Read project updates:  Lincoln Medical School

Throughout the summer, the following planned works will be taking place across the University estate:

Planned Works Buildings Date
Staircase modifications are taking place to increase safety in two buildings. This work is scheduled daily between 08:00 –  17:00 for 4 weeks. There may be some noise disruption from drilling. Emergency access to stairways will be maintained.

Minerva Building

Alfred Tennyson Building

Approximate finish date: Mid-August 2020
Conversion of former County Kitchens Space into Offices. Contractors are currently carrying out project works. Works will not impede access into the building. Minerva House (Holbeach) Approximate finish date: Mid-August 2020
Amber Fire will be on-site to carry out passive fire protection works and internal alterations.

Engine Shed

Lincoln Performing Arts Centre

Starts 20/07/20

Completion end of July

Reroofing will be taking place until the end of July at Witham House. Access to the building will be maintained. Witham House Starts 16/07/20 – Completion end of July
Amber Fire will be on-site to carry out fire stopping to wall, floor and ceiling compartmentation lines (access to all rooms and ceiling voids required). Access will be maintained during this period. Joseph Banks Laboratories Starts 20/07/20 – Completion end of July
Siemens are in the process of conducting fire alarm upgrades to control panels across campus. No fire alarms will be taken out of service and this work isn’t regarded as intrusive. Works will be specific to areas that the control panels are based only.

Engine Shed

Enterprise Building

Lincoln Performing Arts Centre

University Library

For one week commencing 20/07/20

Alfred Bagnalls will be carrying out external decorations on the Brayford Campus.

All fire exits, entrance ways and pedestrian routes will be kept clear at all times.   A cherry picker will be used for the high-level décor.

This work is not considered to be intrusive.

The Swan

Student Wellbeing Centre

Health Centre

Monday 20th July – 31st July 2020

Throughout June and July 2020, our Estates Team and contractors are currently carrying out works to enable reopening of buildings across the estate. These include but are not limited to;

  • Condition surveys
  • Water flushing of buildings
  • Fire extinguisher servicing
  • Space management and allocation
  • Installation of new wayfinding signage and floor markers

Works will be communicated to authorised building users. If you require further information, please contact the Estates Support Desk on estatessupport@lincoln.ac.uk

Across all campuses  June, July, August.
Evaccess with be onsite WC 6th August to carry out the servicing of the Evacuation Chairs, Evaccess have advised if anyone should require the use of the chair they will take this into consideration. Brayford Campus 6th August
GEZE will be servicing the shutters onsite across campus. We do not expect any disruption from these works. Brayford Campus 13th & 14th August

Lighting protection remedial works are due to take place for one week from 11th August.

Although these works are external, there will be some noise disruption during this maintenence due to excavation.

Works will also cause some dust, but this will be kept to a minimum.

  • Chaplin Hall
  • Engine Shed & Lincoln Performing Arts Centre
  • Harvey Hall
  • Isaac Newton
  • Janet Lane-Claypon Building
  • Nicola de la Haye Building
  • Peter de Wint Building
  • Sports Building
  • Stephen Langton Building
W/C 11th August

If you have any queries, please don’t hesitate to contact the Estates Support Desk on estatessupport@lincoln.ac.uk