The following external repair and decoration works will be commencing from 14th June 2021.
Contractor – Bagnall’s Painting and Decorating
Programme:
Building | Start Date | Completion |
Minerva Building | 14/06/21 | 3 weeks |
Arts Bridge | 28/06/21 | 3 weeks |
One Campus Way Plant / Lift Lobby | 30/06/21 | 3 Days |
Sports Hall and HPC | 05/07/21 | 3 weeks |
Rural Science | 14/07/21 | 3 weeks |
Plowright House | 16/06/21 | 3 weeks |
Riseholme Old Hall | 14/06/21 | End of July |
These works should be minimally disruptive. Please contact the Estates Support Desk with any queries at estatessupport@lincoln.ac.uk