ANPR infrastructure installation

ANPR infrastructure installation begins 26 September until 4 October inclusive.

Please see below the schedule of works in the following order:

  • Electrical connections made to camera locations
  • Camera installation P8 By Security Hut includes groundwork on paved areas to feed power
  • Camera installation P12 CSB car park rear end external plant compound, including groundwork to feed power
  • Camera installation P4 Minerva rotunda including groundwork for power supply and the rear of the Alfred Tennyson Building
  • Camera installation P1 One Campus Way including groundwork for power supply
  • Camera installation P1 One Campus Way rear end of road
  • Riseholme Park Campus, Lawress Hall main entrance will include groundworks on verge
  • Campus entrance adjacent to Riseholme Church including groundworks for power supply

Access will be maintained during these works to all buildings and roads on site.

We apologise for any inconvenience caused. Queries can be directed to estatessupport@lincoln.ac.uk